The Jamestown splash pad project has been held up and construction will not begin until August. Chief Financial Officer Gail Dishmon said COVID supply chain delays were at the root of the setback. Dishmon said delays were also caused because of having to change names on the contracts when a new administration took over in Jamestown. “We actually signed the ... Read More »